Thursday, October 11, 2012

Wk 6 - Analyzing Scope Creep


Analyzing Scope Creep

A professional project I was involved with that experienced scope creep was a project with the training and instructional design department at my work where I was acting as the SME.  The project involved the ID/training department soliciting my input and expertise as the SME for some old training documents that needed to be updated due to a change in the process that was outlined in those documents.  The new process indicated that instead of DMT employees emailing information directly to their co-workers personal Outlook email accounts for verification, the DMT employees should now email information on documents to a shared role account through Outlook that had been set up so that there was visibility should someone be out of the office and not checking their personal Outlook email account.
The specific scope issues that we encountered included the fact that the new process that had been developed didn’t take into account that many employees worked remotely and so they would need to access the shared role account through signing onto the network which they were not accustomed to doing due to its unreliable access.  The employees were used to accessing their Outlook email accounts through webmail.  Due to this development, the training/ID department also needed to address the IT aspect of the project with working with the employees to figure out how to set up access appropriately and manage their workflow without interruption.  This additional piece of training and documentation for the project ended up pushing back many of the anticipated deadlines.  At the time, I continued to advise on my pieces of the project as I could in order to keep up with deadlines but many essential meetings had to be coordinated around the new developments.  If I had been the PM, I definitely would have taken the time to gather more detailed information on the different types of employees that were to be affected by the new changes and make sure I knew what their potential concerns were before mapping out the schedule of the project.